Race for convention centre deadline

A_060713HOSSPLCONVENTION1_620x310SkyCity has unveiled an artist’s impression of the proposed Convention Centre, but no start has been been made on construction, and no consent applications have been lodged.

SkyCity’s international convention centre is facing a tough deadline with nothing built, no land cleared so it can be built and no consents applied for so building can start.

SkyCity and the Government have a September 2017 completion date for the centre and a three-year construction time.

The date is specified in the contract between the two parties, in which the casino company agreed to pay $402 million to build the convention centre in return for relaxing of gambling laws.

And even if it were met, long-term booking dates for conventions make it unlikely any will be booked before 2019.

Sticking points appear to be design wrangles between SkyCity and the Auckland Council. The council has objected to some aspects of the design, including the air bridge SkyCity wants to link the casino and convention centre.

Economic development minister Steven Joyce said the deadline was “challenging”.

“It all depends on the process it has to go through for the Resource Management Act consenting process. That depends a fair bit on the design and how it fits into the permitted envelope.”

He said the September 2017 date was still the goal.

Mr Joyce said there had been no change in SkyCity’s contribution or the Government’s concessions.

The contract with the Government shows the gambling concessions take effect when building starts. It also shows the casino company has a lot of room to move the 2017 deadline, with years of grace before it is in breach.

Auckland Council economic development manager Harvey Brookes said staff were working with SkyCity to “help ensure the facility meets Auckland Council’s design aspirations”.

He said no consent had been sought, and it was not possible to know whether it would have to be publicly notified until the application had been submitted.

Conventions and Incentives New Zealand chief executive Sue Sullivan said bookings for large conventions were made four to five years ahead.

There was “significant interest” in the SkyCity project, but bookings wouldn’t come until building started.

“No one will start talking about a venue until they have good, firm dates.

“When they get firm dates, and some have said when the first sod is turned, then they will be out.”

A year after signing the contract, SkyCity doesn’t have an executive with a permanent responsibility for the project. The “project director” who started last November has recently left. A SkyCity spokeswoman said a new director was being recruited.

She said the company hoped to put a resource consent application in before the end of the year.

“The date of project completion depends on when resource consent is approved. An opening date will become clearer once resource consent has been granted.”

Source:

NZ Herald

Sports hub plan goes before council

sportAn ambitious concept plan for a $107 million sports hub in the southwest of Christchurch has been unveiled…

For more follow the link below;

http://www.christchurchrebuild.co.nz/?p=1790

Civil servants back to CBD

gerry_brownlee_4f32d59285More than 1000 government staff will work in central Christchurch by 2016, dispelling the notion of a ”doughnut effect” in the city, Earthquake Recovery Minister Gerry Brownlee announced today…

For more follow the link below;

http://www.christchurchrebuild.co.nz/?p=1782

Bold vision for port’s potential

portCafes, bars and a commercial marina are part of Lyttelton port’s vision for public access onto the harbour front…

For more follow the link below;

http://www.christchurchrebuild.co.nz/?p=1779